Plan around summer heat and the HVAC installer
Menifee has hit 117°F, and summer attic temperatures make long shifts unsafe, so we book attic and duct removal early in the morning or outside peak heat when the schedule allows. If your old system has already failed in July, arrange portable cooling for the rooms you are living in while the work area is sealed off.
The order matters. Survey first, then removal, then a clearance check, and only then the HVAC crew. If the job is big enough to need a district notice, that notice adds at least 10 working days, so we like to test the ducts early, before the HVAC installer has opened the system.
In a Sun City ranch house the ducts usually run through the attic right above the sprayed ceiling texture, so one survey visit can sample both. See asbestos popcorn ceiling removal for the ceiling side. Floors, mobile homes and demolition are on the homepage.