Asbestos survey of a fire-damaged house before demolition
Example project
- Home
- Board-sided 1950s house in Hemet, small and single-story
- Original request
- Demolish the house after a kitchen fire at the back left it unsafe
- Testing
- Survey of the house and the fire debris, inside and out, about 20 samples
- Found
- Asbestos in the ceiling texture, including the burned pieces that fell in the kitchen
- Clear
- No asbestos in the board siding, roofing or floor tile
- Timeline
- One visit, a written survey within a week, then the 10-working-day notice
- Estimated survey cost
- $1,150
In this example, a kitchen fire at the back of a small 1950s house in Hemet has left it unsafe, and the owner plans to demolish it. A building damaged by fire, and its debris, still falls under the air district rule, so the survey and a notice 10 working days ahead come first.